Burleson ISD Bond Update: December 10, 2018 Meeting

At the December 10 school board meeting, Burleson ISD Executive Director of Facilities Regi Brackin and Construction Manager Cliff Holden provided an overview of the district’s four concurrent projects.

 

Kerr Middle School at Hidden Creek

Area A (1st floor):

Mechanical is 80% complete.

Electrical is 80% complete.

Framing is 95% complete.        

Sheetrock is 85% complete.

Windows = Temporary

 

Area A (2nd floor):

Mechanical is 50% complete.

Electrical is 50% complete.

Framing is 80% complete.      

Sheetrock will soon begin.

Windows = Temporary

Roofing is 95% complete.

 

Area B (1st & 2nd floors):

Mechanical is 50% complete.

Electrical is 30% complete.

Framing is 40% complete.

Roofing is 20% complete.

Sheetrock and windows to begin soon.

                   

Area C (1st floor):

Mechanical is 80% complete.

Electrical is 80% complete.

Framing is 90% complete.    

Sheetrock is 10% complete.

Windows are 40% complete.

 

Area C (2nd floor):

Mechanical is 20% complete.

Electrical is 30% complete.

Framing is 30% complete.

Sheetrock is 0% complete.

Windows are at 40%.

Roofing is 85% complete.

 

Area D (Kitchen and Serving):

Mechanical is 30% complete.

Electrical is 20% complete.

CMU walls are 90% complete.

ICF walls are 90% complete.

Steel Structure is 80% complete.

 

Area D & F (Fine Arts):

Mechanical is 10% complete.

CMU walls are 50% complete.

ICF walls are complete.

Steel Structure is 60% complete.

 

Area E & G (Locker Rooms & Gyms):

Mechanical is 10% complete.

Electrical is 10% complete.

CMU walls are 80% complete.

ICF walls are 50% complete.

Steel Structure is 10% complete.

Entire Site: The Site is 80% Complete.

 

Hughes Middle School

Site utilities are 65% complete.

Phase I Progress:

Piers are complete.

Foundation is 80% complete.

Masonry to begin January 2019.

 

Phase II Progress: 85% complete

 

Phase III Progress:

Demolition is 80% complete.

Mechanical/electrical is 15% complete.

 

BHS Multipurpose Facility

Site utilities are 85% complete.

Site excavation is 90% complete.

Site pad is 90% complete.

Foundation/Piers scheduled to begin week of Dec. 17.

Steel delivery scheduled for January 2019.

 

BHS Collaboration Space

Electrical is 98% complete.

Sound and cameras are 60% complete.

Complete: HVAC, ceiling and window walls.

Equipment delivery planned for week of Dec. 10.

Flooring scheduled to be complete by Dec. 13, 2018.

Furniture delivery scheduled for Dec. 18, 2018

 

View pictures on the progress of bond projects here. For information and pictures on all bond project updates, visit bonds.burlesonisd.net.

 